DCA doing checks in stages on klia2 to meet May 2 deadline

19 February 2014 The Department of Civil Aviation (DCA) has started carrying out checks on klia2 and will continue to do so in stages in … Continue reading DCA doing checks in stages on klia2 to meet May 2 deadline

klia2 construction work nearly 100% complete

16 February 2014 Construction work at klia2 in Sepang is nearly 100% complete and the government is confident that the low-cost carrier airport, the biggest … Continue reading klia2 construction work nearly 100% complete

klia2: Worth the Wait, Worth the Pain

14 February 2014 By Kamil Amil Years ago, Sultan Salahuddin Aziz Shah International Airport, or Subang Airport as we all call it, used to be … Continue reading klia2: Worth the Wait, Worth the Pain

Malaysia Airports proposes final single-tier dividend

14 February 2014 Malaysia Airports Holdings Bhd has proposed a final single-tier dividend of up to 6.35 sen per ordinary share but not less than … Continue reading Malaysia Airports proposes final single-tier dividend

Delayed klia2 set for 2 May opening with strong commercial offer

12 February 2014 After a lengthy delay, the new low cost terminal klia2 is set for a 2 May opening with a strong mix of … Continue reading Delayed klia2 set for 2 May opening with strong commercial offer

Initial losses expected for klia2 retail project

12 February 2014 WCT Holdings Bhd expects the group’s third retail project, the upcoming Gateway@Kuala Lumpur International Airport 2, Sepang, to make financial losses in … Continue reading Initial losses expected for klia2 retail project

WCT expects RM70 – RM80 million a year from klia2 Gateway biz

10 February 2014 WCT Holdings Bhd expects its 70:30 joint venture (JV) with Malaysia Airports Holdings Bhd Gateway@Kuala Lumpur International Airport 2, to rake in … Continue reading WCT expects RM70 – RM80 million a year from klia2 Gateway biz

Satisfactory fire safety standards in klia2

10 February 2014 With the fire and rescue system in klia2 now more than 90 per cent completed, the low-cost carrier terminal can begin operations … Continue reading Satisfactory fire safety standards in klia2

80% of retail space in klia2 have been taken up

10 February 2014 More than eighty per cent of the commercial retail space in klia2 have been taken up, and a big number of these … Continue reading 80% of retail space in klia2 have been taken up

klia2 sees 80% of business space taken up

10 February 2014 Eighty percent (80%) of the business space at the low cost carrier terminal (LCCT), klia2, has to date been taken up, said … Continue reading klia2 sees 80% of business space taken up

No compromise on klia2 safety

7 February 2014 The Government will not compromise on safety involving the klia2 project, Acting Transport Minister Datuk Seri Hishammuddin Hussein said. Stressing that the … Continue reading No compromise on klia2 safety

Nurul: Hisham must explain klia2 delay

6 February 2014 Acting Transport Minister Hishammuddin Hussein must explain how he concluded that klia2 was 98% complete and will open on May 2, when … Continue reading Nurul: Hisham must explain klia2 delay

Transport Ministry plays down safety issues at klia2

6 February 2014 By Eva Yeong The Transport Ministry (MOT) has played down safety issues at the main terminal bulding of klia2, and dismissed talk … Continue reading Transport Ministry plays down safety issues at klia2

Deadline on klia2 remains, says Hisham

6 February 2014 by Lee Yen Mun The Government is not budging from its guarantee that klia2 will take off from May 2. klia2 will … Continue reading Deadline on klia2 remains, says Hisham

What is the truth about klia2 opening delays

6 February 2014 BY B.K. SIDHU Nearly two months ago, there were reports stating that klia2 would surely get its certificate of fitness by the … Continue reading What is the truth about klia2 opening delays

klia2 fails to get fitness certification

5 February 2014 BY B.K. SIDHU klia2 looks set to be delayed yet again. About two thirds of the main terminal building have yet to … Continue reading klia2 fails to get fitness certification

UEM & BinaPuri miss Jan 31 deadline for klia2

4 February 2014 klia2, which has only three months to go before it is due to open its doors to passengers and airlines alike, looks … Continue reading UEM & BinaPuri miss Jan 31 deadline for klia2

klia2’s self-tagging, bag drop and next-gen kiosks

30 January 2014, By Ryan Ghee AirAsia: klia2’s self-tagging, bag drop and next-gen kiosks will redefine the airport experience in Asia On 2 May 2014, … Continue reading klia2’s self-tagging, bag drop and next-gen kiosks

RHB Research upgrades MAHB to Buy

28 January 2014 RHB Research has upgraded MAHB to Buy following the 11% stock retracement when it downgraded the company to Neutral. “However, the earnings … Continue reading RHB Research upgrades MAHB to Buy

MAHB 4Q profit falls 38% to RM49m

27 January 2014 Malaysia Airports Holdings Bhd (MAHB) final quarter net profit fell 38% to RM48.51 million from previous year’s corresponding quarter on lower construction … Continue reading MAHB 4Q profit falls 38% to RM49m

2013 tourism target revised due to haze, GE13, klia2 delay

22 January 2014 Haze, the 13th General Elections and the delay in the completion of klia2 were three major reasons why Malaysia was forced to … Continue reading 2013 tourism target revised due to haze, GE13, klia2 delay

klia2 bloats to RM4 billion due to changes in plans

16 January 2014 The increased cost in the construction of klia2 to RM4 billion is due to the “ever-changing aviation industry”, revealed Public Accounts Committee … Continue reading klia2 bloats to RM4 billion due to changes in plans

Domestic airlines to continue increasing capacity in 2014

10 January 2014 Malaysia Airlines (MAS), AirAsia, AirAsia X and Malindo Air are expected to continue increasing capacity this year, especially with the opening of … Continue reading Domestic airlines to continue increasing capacity in 2014

klia2 on track, cost still within RM4 billion

8 January 2014 The total cost of klia2 is not expected to exceed RM4 billion and is on track to open on May 2 this … Continue reading klia2 on track, cost still within RM4 billion

klia2 On Track For Certification

8 January 2014 The low-cost terminal, klia2, is likely to receive the Certificate of Completion and Compliance (CCC) by month-end, says acting Transport Minister Hishamuddin … Continue reading klia2 On Track For Certification

klia2 now 98% completed

8 January 2014 klia2 is in need of a mere 2% of work to be completed before the much-anticipated new terminal is ready for full … Continue reading klia2 now 98% completed

klia2 on track to open on May 2

7 January 2014 The highly-anticipated new Kuala Lumpur International Airport 2 (klia2) is on track to open by May 2 this year. Acting Transport Minister … Continue reading klia2 on track to open on May 2

klia2 to get certification by month-end, says Hishamuddin

7 January 2014 The new low-cost terminal, klia2, is likely to receive the Certificate of Completion and Compliance (CCC) and the Operational Readiness and Airport … Continue reading klia2 to get certification by month-end, says Hishamuddin

Malaysian ‘air fare war’ coming to an end in 2014

2 January 2014 The Malaysian aviation sector has had a turbulent 2013 due to price war and overcapacity that decimated yields and profitability. While the … Continue reading Malaysian ‘air fare war’ coming to an end in 2014

Posts navigation

Previous page Page 1 … Page 3 Page 4
klia2.info is not affiliated, associated, or in any business relationship with Malaysia Airports Holdings Berhad (MAHB), the management company operating the KLIA and klia2 airport. This website is not subsidized, funded, sponsored, endorsed, officially approved by MAHB or any airlines, food, telco, transport and many other companies mentioned on the website. You can read more about us. Please also review the privacy policy.